Accounting for Construction Contracts

Jun 6
06:09

2011

Rashid Javed

Rashid Javed

  • Share this article on Facebook
  • Share this article on Twitter
  • Share this article on Linkedin

A contract is a big job requiring considerable length of time to complete and comprising activities to be done outside the factory promises, viz. construction of a dam or school building, laying down railway lines, etc. Since each contract involves considerable resources both in terms of men and materials, it is necessary to devise an appropriate accounting system to ascertain the cost and profit made on each contract separately.

mediaimage
A contract is a big job requiring considerable length of time to complete and comprising activities to be done outside the factory promises,Accounting for Construction Contracts Articles viz. construction of a dam or school building, laying down railway lines, etc. Special cost and financial accounting is required to maintain the records of construction contracts. Since each contract involves considerable resources both in terms of men and materials, it is necessary to devise an appropriate accounting system to ascertain the cost and profit made on each contract separately.

Profit on incomplete contracts: At the end of an accounting period it may be found that certain contract have been completed while others are still in process and will be completed in the coming years. The total profits made on completed contract say be safely taken to the credit of the profit and loss account. But the same cannot be done in case of incomplete contracts. These contracts are still in process, and there are possibilities of profits being turned into to losses on account of heavy rise in prices of materials and labor and losses on account of other unforeseen contingencies. At the same time it does not also seem desire able to consider the profits only on completed contracts and ignore completely incomplete ones because this may result in heavy fluctuations in the figure of profit from year to year. A year in which a large number of contracts have been completed will show an abnormal high figure for profit while reserve may be the case in the year in which a large number of contracts remain incomplete. Therefore, profits on incomplete contracts should be considered, of course, after providing adequate sums for meeting unknown contingencies.

There are no hard and fast rules for the calculation of the figures for profit to be taken to the credit of profit and loss account. However, the following rules may be followed:

(a) Profit should be considered in respect of work certified only, work uncertified should always be valued at cost.

(b) No profit should be taken into consideration if the amount of work certified is less than 1/4 of the contract price because in such cases it is not possible to foresee the future clearly.

(c) If the amount of work certified is 1/4 or more but less than1/2 of the contract price, 1/3 of the profit disclosed, as reduced but the percentage of cash received from the contractee, should be taken to the profit and loss account. The balance should be allowed to remain as a reserve.

(d) If the amount of work certified is very much near completion, if possible the total cost of completing the contract should be estimated The estimated total profit on the contract then can be calculated by deducting the total estimated cost from the contract price. The profit and loss should be credited with that proportion of total estimated profit on cash basis, which the work certified bears to the total contract price.

(f) The whole of loss, if any, should be transferred to the profit and loss account.

Cost Plus Contracts: In certain contracts the contractee agrees to pay to the contractor the cost price (usually prime cost) of the work done on the contract plus an agreed percentage thereof by way of overhead expenses and profit. Such contracts are known as cost-plus contracts. The system of cost plus contract costing is employed in cases where it is very difficult for the contractor to quote the contract price because there has been no precedent which he may take as basis. It is also employed where the work to be done is not fixed at the time of placing order for the contract. The method is generally used where government happens to be the contractee. The method suffers from the following disadvantages:

There is no incentive to the contractor to eliminate waste and economies the cost of completing the contract. On the other hand, he is tempted to increase the cost because greater the cost, the greater will be his share of profit. In case of this system the amount of overheads recovered and profit made depends upon the value of materials used, which is subject to considerable price  fluctuations. The agreed fixed percentage may, therefore, prove to be either too excessive or too low for covering overheads and profit.

Escalation Clause: Escalation clause is usually provided in the contract as a safeguard against any likely changes in the prices of utilization of material and labor. The clause provides that in case prices of items of raw materials, labor, etc. specified in the contract, change during the execution of the contract, beyond a specified limit over the price prevailing at the time of signing the agreement, the contract price will be suitably adjusted. The term of the contract specify the procedure for calculating such adjustment in order to avoid all future disputes. Thus, such a clause safeguards the interests of both the contractor and contractee in case of fluctuations in the price of materials and labor, etc.

Work in Progress: At the end of the accounting period a contract may still be in progress. The term work in progress refers to the work done so for in respect of the contract, which is still incomplete. It consists of the following:

(1) Working Certified: It refers to the work approved by the contractee. In case of contracts it is the useful practice for the contractor to get the work approved from time to time from the contractee. This is helpful to the contractor in two ways; first in case the contractee finds the work not up to specifications, he may ask the contractor to take corrective actions in time. Second, in contract accounts it is useful practice to have a system of progress payments, i.e., the contractee agrees to pay a certain percentage of the work certified (say, 80 or 90 percent). This is advantageous to the contractor since he gets immediate liquid funds.

(2) Work Uncertified: It refers to the work which has been done by the contractor but not so far approved by the contractee.

Work certified generally includes some profit element also while work uncertified is always valued at cost to the contractor.

Sub Contracts: The contractor may entrust some portion of the work to be done under the contract to a sub-contractor. Usually work of a specialized nature, i.e., steel work, special flooring, etc., is done by sub-contractors, who are responsible to the main contractor. The cost of such sub-contracts is a direct charge against the contract for which the work has been done.